August Updates
Check out our DMP updates for August!
August Updates
-
End-to-End connectivity project is 85% complete as last of equipment has arrived and being installed. All work to be completed prior to end of fiscal year.
Please refer to website for any Broadband updates within the city."
For full broadband updates, please go HERE.
-
Phase 2 and Phase 3 of the project scheduled Q4 of 2023.
-
Data 101 Curriculum is being finalized. Train the Trainer model will be utilized to complete employee training in Q4.
-
Draft Information Technology Disaster Recovery Plan (DRP) is in progress and will be ready for testing at the scheduled tabletop exercise. Any learnings will be incorporated prior to final approval of DRP.
-
Work continues to be completed.
-
Development of backend solution architecture underway.
-
On hold until resources are available.
-
On hold until resources are available.
-
On hold until resources are available.
-
Information Technology Security Management Plan has been created. A tabletop exercise is schedule and learnings from this will incorporated prior to final approval.
-
Draft vendor management templates are in progress including policies and procedures, 3-Year Road Map, 90-Day Plan, Quick Win identification and reports.
-
Procurement for new website re-design and development has commenced. Web Content Audit Updates have been deployed, with over 55+ pages being updated, sunset, re-written and moved into better site locations. Information Architecture is being rolled out as content is re-worked. Current document inventory is scheduled to be completed in Q4.