July Updates

Check out our DMP updates for July!

July Updates

  • All budgeting is updated, all hardware/contracting services have been quoted and we are still just waiting on hardware to be delivered

    For full broadband updates, please go HERE.

  • Final report for Phase 1 (Data Discovery) is complete. Findings of the report have been presented to applicable groups and SLT throughout the month of June. Phase 2 and Phase 3 of the project will start in September 2023.

  • Data Training Curriculum initial program development will start in August 2023.

  • In flight, approximately 60% complete. Team is currently on Milestone 3/4, and conducting tests to validate recovery workflows, identify weaknesses, assess readiness, simulate different scenarios, and ensure business continuity.

  • Directives continue to be developed.

  • On hold to restart August 2023

  • Scheduled 2024

  • Scheduled 2024

  • Scheduled 2024

  • Completed documentation and scheduled tabletop exercise in September.

  • In progress of finalizing vendor management templates, items such as the Vendor scorecard, Relationship Alignment Document and Business Alignment Meeting agenda. The remainder of the phase 2 tasks have been postponed to August due to conflicting priorities.

  • Web Content Audit changes are starting to be rolled-out over the next month to prepare for a better user experience. This includes a document inventory, 50+ pages being updated with revised content, and a full Information Architecture update that will provide a better UX/Navigation workflow.