July Updates
Check out our DMP updates for July!
July Updates
-
All budgeting is updated, all hardware/contracting services have been quoted and we are still just waiting on hardware to be delivered
For full broadband updates, please go HERE.
-
Final report for Phase 1 (Data Discovery) is complete. Findings of the report have been presented to applicable groups and SLT throughout the month of June. Phase 2 and Phase 3 of the project will start in September 2023.
-
Data Training Curriculum initial program development will start in August 2023.
-
In flight, approximately 60% complete. Team is currently on Milestone 3/4, and conducting tests to validate recovery workflows, identify weaknesses, assess readiness, simulate different scenarios, and ensure business continuity.
-
Directives continue to be developed.
-
On hold to restart August 2023
-
Scheduled 2024
-
Scheduled 2024
-
Scheduled 2024
-
Completed documentation and scheduled tabletop exercise in September.
-
In progress of finalizing vendor management templates, items such as the Vendor scorecard, Relationship Alignment Document and Business Alignment Meeting agenda. The remainder of the phase 2 tasks have been postponed to August due to conflicting priorities.
-
Web Content Audit changes are starting to be rolled-out over the next month to prepare for a better user experience. This includes a document inventory, 50+ pages being updated with revised content, and a full Information Architecture update that will provide a better UX/Navigation workflow.